IU QuarkNet meetings
Saturday, March 3, 2001
Meeting Place-Classroom Swain Hall West 135
Meeting time 9:30 AM-3:00 PM
Attendance: Rick Van Kooten, Dave Blair, Matthew Hitchings, James Glen, Rob Spencer, Tim Receveur, John Taylor, Robert Deirth.
The morning was spent discussing the agenda items. The afternoon was a working session where Rob was responsible for drafting the student application, John was drafting a schedule for the workshop and other activities, Dave wrote a letter to Eisenhower for additional funding, Rick began preparing to order items that would be needed
Agenda:
Discuss the recruitment process
A review of all present indicated that Matt was expecting 3-4 applications; Dave, 6 Jim, 3-4; John 4; Rob, 12 and Robert 3. The application was discussed and the IU Cyclotron application was printed for reference. Rob agreed to draft an application. The areas to be addressed by the application were discussed and the following areas were identified to become parts of the application:
We agreed to complete the
application process by next meeting.
John agreed to draft a schedule
for the summer that would include activities that students could participate in
after the workshop day.
Discuss school technology
assets to be provided
Dave will bring up the possibility of Eisenhower
funding
The computers supplied by schools were discussed and no real problems were revealed. Schools place filtering on information entering the school and they also limit links from the outside to the school servers. There are significant firewalls that would prevent access to the sites. We agreed that the web site should be at Indiana University Physics, for the data stream. Schools would FTP data to this site, as well as maintain a local site for their school even though it could not be seen from outside the school.
Discuss electronic and
mechanical planning
Rick and ordering status/plans
Rick reports that the money has arrived and can be spent. Rick discussed the how to calculate how thick the scintillating material needed to be. Matthew took notes from the board, and is writing them up. When the copy is available, it will be scanned and added to these minutes.
Discuss tasks and assignments
Rob—application et
al.
John—workshop schedule et
al.
Dave—Eisenhower
Rick—Ordering scintillation
plastic
Dave—set up meeting for web
site
Discuss schedule for remaining
meeting days
The next meeting day was set for
April 7
Rough schedule for summer
workshop (June 11 through 15)
Will be prepared by John et al.